We are currently in the process of moving the acceptance environment to AWS. We expect this phase to be completed by May 23rd, and the cutover is currently planned for May 27th.
Please note that we might still encounter some unforeseen issues, which would delay the cutover date. We will inform you of the final go/no-go decision on May 25th. On the day of the cutover, the acceptance environment will not be available.
The production migration is scheduled to be finished in July/August; the final cutover date will be announced at least 2 weeks in advance and will take place at a weekend. We will retain our current IP addresses, so there are no changes needed on your side.
Benefits of AWS versus our Private Cloud:
The new IP addresses associated with the migration can be found here.